Flagstone Walkway Repairs

Status: Completed (November 2025)

Overview

In 2025, the Association prioritized the repair of the community walkways to address safety and aesthetic conditions. The Board initiated this process in May 2025, leading to a competitive bidding process and the selection of SES Construction to perform the work.

Financials & Timeline

ItemCost
Original Proposal$57,216.00
Change Order (Addt'l Work)$1,344.00
Total Investment$58,560.00

Timeline: Oct 2025 – Nov 21, 2025

The repairs are backed by a one-year labor warranty.

Scope of Work

The project focused on paver walkway repairs at the Vine. The primary scope included removing and replacing stones, grinding or removing roots causing displacement, and filling joints.

Stone & Mortar Repair

The initial assessment required removing and replacing stones in 32 locations and replacing mortar in 21 locations.

Expanded Scope

A Change Order was approved to remove and replace the stone walkway at a specific Unit, identified as a necessary addition by the Board.