Status: Completed — Project was successfully finished on Saturday, April 11, 2026.
Two storm drain inlets located in the sidewalk area near Units 31-34 had become a safety concern. Over time, the grates had sunken down while the surrounding concrete remained elevated, creating a significant tripping hazard for residents and pedestrians.
This project removed the uneven concrete and repoured a smooth, properly sloped surface to sit flush with the drains, successfully restoring the safety of our walkways.
| Payment Schedule | Amount |
|---|---|
| Approval / Mobilization (60%) | $1,782.00 |
| Final Invoice Upon Completion | $1,188.00 |
| Total | $2,970.00 |
The repair focused specifically on the two drains located in front of Unit 31 along the sidewalk.